Loadshedding cost SA R59bn in 2019

New data released by the Council for Scientific and Industrial Research (CSIR) has indicated that South Africa suffered a 2019 loss of between R59bn and R118bn due to loadshedding.

According to the CSIR, the 530 hours of unplanned power cuts during the year occurred at a higher intensity than previous years, including an unprecedented move to Stage 6 loadshedding in December. More energy – approximately 1 352 Gigawatt hours (GWh) – was shed during 2019 than previous years.

The percentage of time that Eskom’s power plants were able to produce electricity was at just 67%.

“Historical fleet EAF decline seems irreversible,” stated the presentation’s authors.

Loadshedding is expected to continue for two to three years, depending on key decisions and actions by government.

The CSIR presentation set out various scenarios for South Africa to ensure the supply of power in the current decade. A key response to start to close the “energy supply gap” is to let businesses, private citizens, mins and farms produce their own electricity.